↑↓ to moveEnter to openAll results →

    Cost and schedule health for every project, without a spreadsheet

    Earned value compares three numbers: what the plan said should be done by now, what has been done, and what it has cost. Lodestar computes them for every active project with a budget and dates, from the same schedule, approvals and spend the rest of the platform uses.

    Earned value table: planned value, earned value, actual cost, CPI and SPI per project
    Earned value. Which projects are buying progress and which are only spending.

    What usually goes wrong

    And what changes when it runs on one model.

    01

    Earned value lives in a spreadsheet

    One analyst rebuilds it each month from exports that are already out of date.

    02

    Progress is whatever was typed

    Earned value built on self-reported completion flatters every project.

    03

    Spend arrives late

    Actual cost is copied from the finance system weeks after the money left.

    04

    A red index leads nowhere

    The report shows a CPI of 0.8 and nobody can open the work behind it.

    Completion counts in full only once it is approved

    Earned value is the project's budget multiplied by its progress, and progress rolls up from the activities on the plan. An activity reported at 100% counts at a capped value, 95% by default, until it is approved.

    • Progress rolled up from weighted activities
    • The cap is set by an administrator
    • Work at 100% but unapproved is listed
    Progress proof: activities approved, pending, rejected, at 100% but unapproved, and missing evidence
    Progress proof. Which completions are backed by approved evidence, and which are still only claims.

    Actual cost from paid invoices

    Actual cost is the project's spent figure, which reads paid invoices first, then spend recorded on budget lines, then a figure entered by hand. Invoices in other currencies are converted to the workspace's reporting currency.

    • Allocated from budget lines
    • Committed from awarded contracts
    • EV, CPI and SPI on the project's financials
    Project financials: allocated, committed and spent, with earned value, CPI and SPI
    Project financials. Allocated, committed and spent, with earned value beside them.

    Spend against progress across the programme

    Every project is plotted by the share of its budget it has burned against the progress it has made, sized by its allocated budget. Projects spending ahead of delivery stand apart from the ones that are balanced, stalled or running ahead.

    • Running ahead, balanced, stalled, overspending
    • Dot size shows the allocated budget
    • Capital at risk totalled
    Chart of projects by budget burned against progress
    Money against mission. Burn against progress for every project.

    A forecast final that is computed

    The estimate at completion is the budget divided by the cost performance index, so a falling index moves the forecast straight away. On the executive dashboard, burn plus the estimate to complete gives the forecast final, with variance against plan by pillar.

    • Cost and schedule variance per project
    • Overrun and underspend flagged in Analytics
    • New projects held in a guard period first
    Budget utilisation: current burn, open commitment, estimate to complete and forecast final, with a burn against plan and forecast chart
    Budget utilisation. Burn against plan and forecast.

    What you get

    Every item runs on the same engines the screens use.

    PV, EV and AC

    Planned value, earned value and actual cost for every active project.

    CPI and SPI

    Cost and schedule indices, with a status for each and one overall verdict.

    Variances and EAC

    Cost variance, schedule variance and the estimate at completion per project.

    Planned value from the plan

    Planned value follows the dated, weighted activities on the schedule.

    Explained on the page

    Each column header explains its measure and shows its formula.

    Financial access

    Money figures are hidden from people without financial access to a project.

    Questions

    Which earned value figures does Lodestar show?

    Planned value, earned value, actual cost, CPI, SPI, cost variance, schedule variance and the estimate at completion, per project. Each project also gets a cost status, a schedule status and one overall verdict: healthy, at risk or critical.

    Do we need timesheets?

    No. Earned value comes from progress on the plan, and actual cost from paid invoices, budget lines or an entered figure. Nothing depends on hours being booked.

    Does it replace our finance system?

    No. The finance system stays the system of record. Its actuals can arrive through the ERP integration and are placed against the budget and the plan.

    Which currency are the figures in?

    The workspace's reporting currency. Invoices in another currency are converted with the exchange rates you configure, so every earned value figure is shown in one currency.

    See it on your own programme.

    Send us a slice of your portfolio and we load it before the session, from strategy down to task.