↑↓ to moveEnter to openAll results →

    Where a slipped date and an unclassified commitment both cost real money

    Capital delivery needs the money and the schedule in one model. Lodestar carries budget, secured, committed, actual, forecast and variance at ledger level, and turns earned value into an early warning instead of a month-end surprise.

    Budget tracking: capital at risk, and a chart of each project's spend against its progress
    Money against mission. Every project placed by spend against progress, with the capital at risk.

    How it works

    For capital delivery, where a slipped date and an unclassified commitment both cost real money.

    Six numbers, one truth, no spreadsheet in between

    Budget, secured, committed, actual, forecast and variance live on the same record as the schedule, so a commitment without a classification, or spend ahead of progress, is caught as soon as it happens.

    • Ledger-level actuals from the finance system, not retyped
    • Unclassified allocations and leakage risk flagged on sight
    • Forecast final recomputed as the plan changes
    Project financials: allocated, committed and spent, with earned value, CPI and SPI
    Project financials. Allocated, committed and spent, with earned value beside them.

    Earned value as an alarm, not a report

    CPI and SPI are computed per project and rolled up, so the programme knows which packages are buying progress and which are only spending.

    • EV, CPI, SPI and EAC per project and per pillar
    • Burn running ahead of progress flagged as its own condition
    • A breach projected weeks before it lands
    Earned value table: planned value, earned value, actual cost, CPI and SPI per project
    Earned value. Which projects are buying progress and which are only spending.

    One moved date, priced across the whole portfolio

    When a date moves, the engine simulates the ripple, including the undeclared dependencies Polaris finds, and prices it in days of end-date impact and cost.

    • Second-order effects computed by the engine
    • Undeclared links surfaced and proposed for confirmation
    • The committee pack shows the costed consequence
    Delay simulator: a 45-day delay on one activity shifts the programme end date and extends two people's assignments
    Delay simulator. What a 45-day slip does to the end date and to the people on the work.

    The capital delivery toolkit

    Every item below runs on the same engines the screens use, so the numbers never diverge.

    Ledger-level finance

    Budget, secured, committed, actual, forecast and variance on one record.

    Earned value

    CPI, SPI and EAC computed per project and rolled up.

    Forecast engine

    Forecast final recomputed as dates and commitments change.

    Dependency hunter

    Undeclared links found and priced in days of end-date impact.

    Contingency simulation

    Test a drawdown in a sandbox before anyone signs for it.

    Leakage detection

    Unclassified allocations and invoices without a match, flagged.

    Runs on Budget burn engineEarned valueCascade detectorScenario engineFinancial advisor

    The overrun caught while it is still a decision, not a disclosure.

    See it on your own programme.

    Send us a slice of your portfolio and we load it before the session, from strategy down to task.